Installation of BWTS system in void space on a RoRo ship. The installation was completed in 12 days, including modification of existing systems and installation of new stripping ejector.
Additionally, a grating platform, safety systems and lighting were added in the void.
Project completed together with our long-term partner ecomar
Major challenges included a short timeframe and very limited space for the installation.